This week we performed the final volume and pressure test. The pressure test showed that there were no leaks in the welds and that everything was able to be pressurized to at least 10 PSI without a failure of the tank. The final volume including the foam displacement and filler neck was shown to be 1.515 US gallons.

This week there was also a significant portion of progress made on the final report and presentation.